Availability Check in Delivery
Availability check in SAP Delivery is initiated during creation and check is done for the picking date. The check is carried out on the same criteria as in Sales order processing. Availability check at delivery level is carried out for following reasons. Check may not have done for items at order level and hence needs to be done at delivery stage. Although check may have been carried out in order the availability situation may have changed due to various unknown reason. Dynamic check at this stage would ensure correct status in termsof availability so that further actions after delivery i.e. Picking, Packing etc are not affected.
Control elements for availability are same as in sales documents
- Checking Group
Checking group specifies in combination with checking rule the scope of availability check. It is maintained in material masterin Plant view and copied on to sales documents. - Checking Rule
A Checking rule is assigned to each transaction and in combination with checking group define what movements are considered for availability check. These are predefined in system - Delivery Item category
Additional check exists at delivery item category level to control if availability should be checked or not.
Prerequisites
Following prerequisites need to be fulfilled for availability check to take place
- Control elements in Sales and Distribution are maintained in customizing and assigned.
- Availability check switched on at requirement class and deliveryitem category level.
- Plant should be defined at document item level.
- Checking group should be maintained in material master on Sales/plant screen in Availability check field.
Scope of Check
Elements that can be included in availability check are
- Stock
- Safety Stock
- Stock in Transfer
- Quality Inspection stock
- Blocked Stock
- Inward/Outward movement of goods
- Purchase orders and requisitions
- Planned orders and Production orders
- Reservations
- Dependent requirements
- Sales and Delivery requirements
The elements that need to be included depend on the scenario for which availability check is being set.
Process Flow
System determines date for availability check on basis of earliest material availability date of all schedule lines in delivery.
If there is insufficient stock following is system behavior
- Sufficient quantity of material not available by material availability date, a delivery quantity ‘0’is entered in delivery. If item category of delivery permits ‘0’quantity then it would be included else item would not be allowed in delivery.
- Quantity available of material is lower than order quantity, system would enter available quantity as delivered quantity and order would get updated accordingly. If partial delivery is not allowed, this would be noted in delivery creation log.
If you like this post, you may as well like these too:
- Availability Check & TOR in Sales in SAP, Availability check is one of the key functionality in sales document processing. The confirmation of delivery of goods to customer while entering a sales document is carried out...
- Pricing in Delivery Pricing is an intrinsic part of Sales & Distribution. System has provided extensive features to map various pricing scenarios in business environment. ‘Pricing’ term is used to explain the calculation...
- Planned Delivery Costs and Un-Planned Delivery Costs Planned delivery costs are entered at the time of Purchase order. At goods receipt, a provision is posted to the freight or customs clearing account. e.g. FRE is the account...
- CHECK : ABAP Keyword a day CHECK Within loops and events- CHECK logexp.Special for reports with logical databases- CHECK sel.- CHECK SELECT-OPTIONS. CHECK – within loops Basic formCHECK logexp.EffectCHECK evaluates the subsequent logical expression . If...
- Configure Check Deposits The following are the steps for configuring check deposit: Create account symbols for the main bank and incoming check account. Assign accounts to account symbols. Create keys for posting rules....
- Delivery Processing in SAP Sales and Distribution Delivery forms the central object in Logistics Execution module. Outbound delivery supports all shipping activities like Picking / Packing, Transportation & Goods Issue. In outbound delivery process planning of shipping...
- AUTHORITY-CHECK : ABAP Keyword a day AUTHORITY-CHECK Basic formAUTHORITY-CHECK OBJECT objectID name1 FIELD f1ID name2 FIELD f2…ID name10 FIELD f10.EffectExplanation of IDs:object Field which contains the name of the object for which the authorization is to...
- ABAP Programs: Type check for form parameters REPORT ZSOURCE1007.* Types and variables for later useTYPES: T_NAME_1(20), T_NAME_2(20).DATA: NAME_1 TYPE T_NAME_1, NAME_2 TYPE T_NAME_2.* Calling forms with different actual parametersPERFORM SET_NAME_LIKE CHANGING NAME_1.PERFORM SET_NAME_LIKE CHANGING NAME_2.PERFORM SET_NAME_TYPE CHANGING...
- SAP Cash Management FAQs – Check Deposit Overview 1. True/False? The SAP principle for the bank statement processing and the check deposit processing is the same. 2. True/False? The check deposit processing cycle is completed with the bank...



















Leave a Reply