From the IMG Screen: Materials Management è Consumption-Based Planningè Plant Parameters è Carry Out Overall Maintenance of Plant Parameters


Click on the Create button

Enter your Plant: PT_ _

Click on the Create button

Select Create again to get past information window

Click on the Maintain button twice

 

  • Under the Environment section Click on the Number ranges button
  • Then click on the Planned orders button
  • Assign no. range 01 to your plant

  1. Click Save
  2. Hit the back button
  3. Click on the Reserv./depend.reqmts button
  4. Assign no. range 01 to your plant
  5. Click Save
  6. Hit the back button
  7. Click on the Purchase requisitions button
  8. Assign no. range 01 to your plant
  9. Click Save
  10. Hit the back button
  11. Click on the MRP lists button
  12. Assign no. range 01 to your plant
  13. Click Save
  14. Hit the back button
  15. Click on the Sim. Dependent reqmts button
  16. Assign no. range 01 to your plant
  17. Click Save
  18. Hit the back button twice
  19. Click on MRP controllers button under the Master data section
  20. Click on the New Entries button
  21. Enter your Plant PT_ _

Next you will create an MRP controller (example C_ _) and input a description in the field beside your MRP controller (example Controller C_ _)

  1. Click save
  2. Click exit to return to the maintain plant parameters screen.
  3. Click on the Floats button
  4. Click on the New Entries button
  5. Enter your Plant: PT_ _ and complete the form as shown below:

  • Op.Pd: 1 (Workdays prior to order start)
  • FlBefrePr: 1 (Workdays between order start and scheduled start)
  • FlafterPr: 1 (Workdays between order due date and scheduled finish date)
  • ReleasPer: 1 (Workdays in release period)

Click Save